How long did your FieldPulse rollout take? What slowed you down?

We're about three months into our FieldPulse implementation, and while the team is starting to settle in, I keep thinking about how the timeline compared to what we originally planned. I'm curious about other teams' experiences—both to validate where we landed and to flag anything we might still be underestimating.

Our situation: 18 field technicians across two regions, moving from a mix of paper work orders and shared spreadsheets. We budgeted 6 weeks for full rollout. It took closer to 10, and I'd say we're still refining workflows that weren't fully baked in week 6.

The biggest slowdown for us wasn't the software itself—it was getting our existing customer data clean enough to import without creating a mess. We also underestimated how long it would take to train our longest-tenured techs, who had their own systems they were genuinely effective with.

What did your rollout timeline actually look like versus your plan? And what ended up being the thing that slowed you down most?

Parents
  • We had a similar data cleaning situation. Budgeted 4 weeks, took 7. Pro tip: don't try to migrate everything—identify your top 200 active accounts, get those perfect, and let the historical stuff come over in phases. The team needed to see quick wins with current customers, not spend week 3 arguing about how a job from 2019 got coded.

    Our actual biggest slowdown was dispatcher habits. The software was ready, but we had two dispatchers who'd been doing things a certain way for 12+ years. They weren't resisting change, exactly—they just genuinely couldn't imagine the workflow differently until they sat with someone else's setup. We ended up shadowing another FieldPulse customer for a day, and that unlocked more progress than any training session.

Reply
  • We had a similar data cleaning situation. Budgeted 4 weeks, took 7. Pro tip: don't try to migrate everything—identify your top 200 active accounts, get those perfect, and let the historical stuff come over in phases. The team needed to see quick wins with current customers, not spend week 3 arguing about how a job from 2019 got coded.

    Our actual biggest slowdown was dispatcher habits. The software was ready, but we had two dispatchers who'd been doing things a certain way for 12+ years. They weren't resisting change, exactly—they just genuinely couldn't imagine the workflow differently until they sat with someone else's setup. We ended up shadowing another FieldPulse customer for a day, and that unlocked more progress than any training session.